As for other major construction projects, an environmental impact assessment (EIA) in accordance with Article 10a of the Environmental Protection Act (EPA) must be carried out in the licence procedures for the deep geological repository and for the fuel element packaging facility. The EIAs are used by the federal authorities to check whether the planned facilities comply with the applicable environmental regulations during their construction and operation. The 1st stage EIA is carried out in the general licence procedure and the 2nd stage EIA in the building permit procedure.
As part of the application documents, Nagra must submit an environmental impact report (EIR) in which it sets out the likely impact of the projects on the environment and the measures planned to avoid or minimise this impact. This report is examined by the cantonal and federal authorities, and the result of the examination becomes part of the licence, e.g. in the form of mandatory conditions such as protective or alternative measures.
The effect of the EIA does not begin with the project approval, but already during the project planning phase. The aim is to recognise the environmental impact of the facilities at an early stage and to avoid or limit this impact. For example, environmental criteria were already heavily weighted in the search for locations for surface infrastructure.
In 2015/16, Nagra carried out the first preliminary investigations for the EIA for the three siting regions at that time. Preliminary investigations contain specifications for the EIA and show which questions are to be answered and by which methods.
With the site proposal for the deep geological repository in northern Lägern and for the packaging facility in Würenlingen, Nagra also submitted updated preliminary EIA investigations for these sites in 2022. The examining authorities came to the conclusion that these preliminary investigations largely fulfil the requirements of environmental protection legislation in the 17 environmental areas examined. However, Nagra still had to adapt the specifications for the main inspections in some respects. Based on the information available at the time, the FOEN determined that there were no insurmountable obstacles to licencing from an environmental point of view.
The EIA procedures for the deep geological repository are a special case in that there is a long time lag between the first and second stages, and project components, construction procedures or environmental protection regulations may change in the meantime. The general licence application only sets out the main features of the project and many environmental aspects, such as construction work, cannot yet be finalised.